Suprayogi, Imam and ., Trimaijon and ., Nurdin and Saputra, Rio (2013) POLA PENGOPERASIAN PINTU PEMBILAS TERHADAP LAJU SEDIMENTASI TAHUNAN PADA BENDUNG SEI TIBUN, KABUPATEN KAMPAR, PROVINSI RIAU. Jurnal Teknik Sipil, 12 (2). pp. 145-154. ISSN 1411-660X
|
Text
POLA PENGOPERASIAN PINTU PEMBILAS TERHADAP LAJU SEDIMENTASI TAHUNAN PADA BENDUNG SEI TIBUN KABUPATEN KAMPAR, PROVINSI RIAU.pdf Download (1MB) | Preview |
Abstract
The purpose of this research is setting an operational pattern of the flushing gate due to the annual sedimentation rate in the Sei Tibun Weir, Kampar Region, Riau Province. The problem arouse because there is no operation manual of the flushing gate at the Weir that make the officer difficult to decide the exact sediment flushing time and the size of the flushing gate. The field condition showed that the officer must clean the sediment at the irrigation canal manually, which can be evaded with a routine sediment flushing. The method used to describe the operational pattern of the flushing gate considering the hydraulic aspects was a physical modeling with 1:1 scale, which was the Sei Tibun Weir itself. The actual field condition approached with idealization shapes to simplify the calculation procedure. The main result of this research showed the value of the annual sedimentation rate in the Sei Tibun Weir was 13.320,65 m3/year. In order to achieve a longer service function of the Weir, routine flushing needed every 8 months with the size of the flushing gate was 31.7 cm if one flushing gate operated for 6 hours. If two flushing gate operated in the same duration, the size of the flushing gate was 15 cm.
Item Type: | Article |
---|---|
Uncontrolled Keywords: | sedimentation rate, weir, flushing gate, physical mode |
Divisions: | Fakultas Teknik > Program Studi Teknik Sipil |
Depositing User: | Editor UAJY |
Date Deposited: | 10 Mar 2014 08:00 |
Last Modified: | 12 Mar 2014 08:41 |
URI: | http://e-journal.uajy.ac.id/id/eprint/4903 |